Updates in Dec 2026

 

 

Accommodation Cluster Progress Update

The Accommodation Cluster has progressed substantially, with the main building structures and external architectural works largely completed. Internal building works, including architectural finishes, MEP installation and internal fit-out, are estimated to be approximately 70–80% complete. The current focus is on completing the remaining internal finishes, services installation, furniture and fittings, as well as external access, landscaping and associated site works. Outstanding activities include completion of MEP works, testing and commissioning, rectification and final coordination prior to handover.

Chalets (North & West)

  • External architectural finishes to the chalet blocks substantially advanced, with the main façades, windows and roof elements in place.
  • Internal architectural finishes, fit-out and preparation for furniture and fittings installation are progressing, with overall internal works estimated to be approximately 80% complete.
  • Remaining internal works include completion of outstanding finishes, installation of furniture and fittings, MEP works, testing, commissioning and rectification.
  • Final MEP installation, testing and commissioning are progressing and will be completed in coordination with the remaining architectural and fit-out works.

Bungalows (Pet & South)

  • Internal architectural finishes and fit-out works are progressing, with overall internal works estimated to be approximately 70% complete.
  • Outstanding activities include completion of internal finishes, furniture and fittings installation, MEP works, testing and commissioning.
  • Final MEP installation, testing and commissioning, together with outstanding rectification and coordination works, are ongoing.

Guest Rooms

  • Internal fit-out and finishing works are progressing, with overall internal works estimated to be approximately 70–80% complete.
  • Remaining works include completion of internal finishes, furniture and fittings installation, and outstanding MEP works.
  • MEP installation, testing and commissioning are progressing alongside the remaining internal fit-out works.

Villas (East & West)

  • Internal fit-out and finishing works are progressing, with overall internal works estimated to be approximately 80% complete.
  • Outstanding activities include completion of internal finishes, furniture and fittings installation, MEP works, testing and commissioning.
  • Final MEP installation, testing and commissioning, together with outstanding rectification works, are ongoing.

Swimming Pool

  • The swimming pool is now water-filled in the completed sections, representing a significant change from the earlier stage of waterproofing and tiling works.
  • Poolside deck areas, surrounding hardscape and associated external finishing works remain in progress.
  • Plumbing, filtration, circulation and water-treatment installations, together with system testing and commissioning, are to be completed before the swimming pool is ready for operation.

Accommodation Administration Building

  • Internal fit-out and finishing works are progressing, with overall internal works estimated to be approximately 70% complete.
  • Outstanding activities include completion of internal finishes, MEP installation, testing and commissioning, and final coordination.
  • MEP installation, testing and commissioning preparation works are continuing in parallel with the remaining internal fit-out.

Housekeeping Building

  • Internal fit-out and finishing works are progressing, with overall internal works estimated to be approximately 70% complete.
  • Remaining works include completion of internal finishes, MEP installation, testing and commissioning, and rectification.
  • MEP installation, testing and commissioning are continuing alongside the remaining internal and external finishing works.

 

Recreation Cluster Progress Update

The Recreation Cluster has made substantial progress, with Buildings 1, 2 and 3 largely completed in terms of their main structures and external architectural works. Internal building works, including architectural finishes, MEP installation and fit-out, are estimated to be approximately 70–80% complete. The remaining activities are focused on completing internal finishes, building services, external access, hardscape, landscaping and the surrounding site areas.

Recreational Buildings 1, 2 & 3

  • Recreational Buildings 1, 2 and 3 are substantially advanced externally, with their main façades, glazing, rooflines and architectural feature elements in place.
  • Internal architectural finishes, fit-out and preparation for furniture and fittings installation are progressing, with overall internal works estimated to be approximately 70% complete.
  • Final MEP installation, testing and commissioning, together with outstanding building-services coordination and rectification works, are ongoing.
  • Outstanding external finishing, interface coordination and completion of the surrounding site areas remain ongoing.

Gazebo Units

  • The gazebo structures and their principal external architectural finishes substantially complete.
  • The gazebo structures and their principal external architectural finishes are substantially complete. Remaining works include associated external finishes, landscaping, access and any outstanding services and rectification works.
  • Final coordination and completion of any applicable services, inspections and associated works are ongoing.

 

F&B Cluster Progress Update

The F&B Cluster, including the Terrace Building, has progressed substantially, with the main building structure, envelope and external architectural works largely completed. Internal building works, including architectural finishes, MEP installation and fit-out, are estimated to be approximately 80% complete. The remaining focus is on completing internal finishes, building services, F&B equipment and associated installations, together with the external forecourt and surrounding areas.

  • The Terrace Building's main external envelope and architectural features are substantially advanced, with glazing and façade elements installed.
  • Internal fit-out, architectural finishes and preparation for F&B furniture, fittings and equipment installation are progressing, with overall internal works estimated to be approximately 80% complete.
  • Outstanding activities include completion of internal finishes, F&B equipment installation, MEP works, testing and commissioning, and final building-services coordination.
  • Some external finishing and interface works remain, including the completion of surrounding areas and coordination with the wider site works.
  • External access, paving, landscaping and associated infrastructure around the building continue to progress

4. Substation & Bin Centre

The Substation and Bin Centre buildings are substantially complete. The Substation remains subject to the installation of the relevant electrical equipment by the service provider, followed by the necessary inspections, testing, energisation and clearances. The Bin Centre is also substantially complete, with any outstanding services, inspections and handover requirements to be closed out.


5. General Areas Progress Update

External and common infrastructure works remain a major focus of the project.  Substantial progress to the buildings and landscaped areas, while roads, car parks, pedestrian routes, entrance areas, drainage and external services continue to require coordinated completion.

  • Internal roads and access routes are substantially formed in several areas, with localised paving, surfacing and finishing works still ongoing.
  • Car park areas and associated paving are progressing, with some surfaces and adjoining landscape works still unfinished.
  • The main entrance and approach areas remain subject to external finishing and coordination works.
  • The guardhouse structure is completed and now current on internal areas, completion of the surrounding access, paving and associated works remains ongoing.
  • External drainage and utility infrastructure works continue in conjunction with the road and landscape works.
  • Pedestrian routes and linkways are substantially established in parts of the development, with localised completion and interface works continuing.
  • Landscaping has progressed across the site, with trees, planting and lawn areas established in a number of locations; further softscape and hardscape finishing remains.
  • External MEP services and utility connections, including any required testing and authority interfaces, remain to be verified against the latest services and commissioning records.
  • Coordination of roads, car parks, drainage, utilities, pedestrian access and landscaping remains important to completing the external works as an integrated package.

6. Overall Progress

The project has progressed into the advanced stage of construction, with major building structures and principal external architectural works substantially completed.

Internal works across the Accommodation, Recreation and F&B Clusters are estimated to be approximately 70–80% complete. Remaining works mainly involve architectural finishes, MEP installations, fit-out, furniture, fittings and equipment installation, testing and commissioning.

Within the Accommodation Cluster, the chalets, bungalows, guest-room buildings, villas, Administration and Housekeeping Buildings have progressed substantially. Swimming pool works, poolside decks and associated facilities are also progressing.

The Recreation Cluster buildings and gazebo units are substantially advanced, with remaining works focused on internal finishes, MEP completion and fit-out. The Terrace Building has also progressed well, with F&B equipment installation and external forecourt works outstanding.

The Substation and Bin Centre are substantially complete, subject to equipment installation, inspections and clearances. External infrastructure works, including the guardhouse, entrance roads, car parks, drainage, utilities, pedestrian linkways and landscaping, are progressing.

Overall, the development is advancing towards completion and handover. Key outstanding activities include internal fit-out, MEP completion, equipment installation, external infrastructure works, integrated testing and commissioning, authority inspections, statutory clearances and operational readiness.